Production and Operations Management - 3

POM Assignment
Multiple Choice Multiple Answer
Question
Which of the following aspects are essential to ensure quality of purchased items?
Correct Answer
Defining right quality for the job , Vendor performance evaluation , Making sure that suppliers understand the requirements
Your Answer
Defining right quality for the job , Vendor performance evaluation , Making sure that suppliers understand the requirements

Select The Blank
Question
The ________ breakdowns usually cost more, partly due to damage done to the adjustment components and partly due to emergency actions.
Correct Answer
Unexpected
Your Answer
Unexpected

True/False
Question
After goods have been manufactured, route sheets and operation layouts should not be collected back.
Correct Answer
False
Your Answer
False

True/False
Question
In case of centralised inspection, inspection rooms generally become bottleneck and cause delay in taking action regarding rejection or rework.
Correct Answer
True
Your Answer
True

Multiple Choice Single Answer
Question
MRP is based on the concept of inventory demand which is of following type
Correct Answer
Dependent and independent
Your Answer
Dependent and independent

Multiple Choice Single Answer
Question
Any premise in which persons are employed for purpose of making any product/s is called
Correct Answer
Factory
Your Answer
Factory

Multiple Choice Multiple Answer
Question
Components of Production Management include
Correct Answer
Capacity Planning , Job Design , Production Planning
Your Answer
Capacity Planning , Job Design , Production Planning

Multiple Choice Single Answer
Question
Which of the following is the criteria for the percentage defectives in the zone of the indecision?
Correct Answer
Lots having the percentage defective more than AQL but less than LPTD
Your Answer
Lots having the percentage defective more than AQL but less than LPTD

Multiple Choice Multiple Answer
Question
Which of the following are examples of addition during recording for method study?
Correct Answer
Brazing , Welding , Riveting
Your Answer
Brazing , Welding , Riveting

Select The Blank
Question
The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________.
Correct Answer
Overtime working
Your Answer
Overtime working

Select The Blank
Question
An Ideal OC curve is ________ shaped curve that accpets all the lots with quality equal to or better than AQL .
Correct Answer
Rectangular
Your Answer
Rectangular

Multiple Choice Multiple Answer
Question
Which of the following causes can be responsible for derailing the production schedule in a factory?
Correct Answer
Errors in drawings , Delay in receipt of material from vendor , Excessive absenteeism
Your Answer
Errors in drawings , Delay in receipt of material from vendor , Excessive absenteeism

Multiple Choice Multiple Answer
Question
Which of the following situations demand the economic consideration while selecting a job for method study?
Correct Answer
Unorderly movement of men and materials , Excessive process defectives , Too many suggestions received for improvement from a department or section
Your Answer
Unorderly movement of men and materials , Excessive process defectives , Inconsistent quality

True/False
Question
During set up of X bar-R control chart, control limts should be practically revised from time to time as additional data is accumulated.
Correct Answer
True
Your Answer
False

Multiple Choice Multiple Answer
Question
Which of the following are the basic requirements of quality standard?
Correct Answer
Deifinite , Undesrstandable , Economically viable
Your Answer
Absolute uniformity , Undesrstandable , Economically viable

Match The Following
Question
Correct Answer
Your Answer
Toung
Sweet
Sweet
Eye
Crack
Crack
Nose
Burnout
Burnout
Ear
Impact
Roughness

Select The Blank
Question
The ________ is the defect level for which lots are regarded as bad lots.
Correct Answer
Lot Tolerance Percentage Defective
Your Answer
Acceptable quality level

True/False
Question
Floor inspection delays the identification of faults which can not be rectified immediately before large lots are spoiled.
Correct Answer
False
Your Answer
False

True/False
Question
Cent percent inspection is required on WIP prior to the key, critical or costly operation.
Correct Answer
True
Your Answer
True

Multiple Choice Single Answer
Question
The document which incorporates details of process planning for a job is called
Correct Answer
Route Sheet
Your Answer
Route Sheet

True/False
Question
Repetitive movements between work stations which are difficult to be traced on string diagrams can be conveniently shown on flow diagrams.
Correct Answer
False
Your Answer
True

Multiple Choice Single Answer
Question
Which of the following is the most popular technique for Project Production?
Correct Answer
PERT & CPM
Your Answer
PERT & CPM

Multiple Choice Single Answer
Question
Technique of Value Engineering can be effectively employed in design of a product to
Correct Answer
To meet the intended function at lowest cost
Your Answer
To meet the intended function at lowest cost

Multiple Choice Single Answer
Question
What can be the worst effect due to excessive vibration?
Correct Answer
Breakdown
Your Answer
Breakdown

Multiple Choice Single Answer
Question
What is the relation between duration of an activity and length of an arrow?
Correct Answer
No relation
Your Answer
No relation

Multiple Choice Single Answer
Question
What is the nature of the sampling plan for critical defects?
Correct Answer
Tight
Your Answer
Tight

Select The Blank
Question
The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking.
Correct Answer
Condition monitoring
Your Answer
Condition monitoring

Multiple Choice Multiple Answer
Question
Which of the following are important considerations concerning activity times?
Correct Answer
Activity time should be obtained from the person responsible for the completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available.
Your Answer
Activity time should be obtained from the person responsible for the completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available.

Multiple Choice Single Answer
Question
Which of the following techniques is used by industrial engineering department to obtain the utilisation index?
Correct Answer
Work Sampling Studies
Your Answer
Break Even Analysis

Multiple Choice Multiple Answer
Question
Which of the following factors play important role while selecting or rejecting a particular site from legislation and taxation point of view?
Correct Answer
Labour laws , Building codes , Policies regarding issue of licences
Your Answer
Labour laws , Building codes , Policies regarding issue of licences

Multiple Choice Multiple Answer
Question
Which of the following cases can be referred as operation in method study recording?
Correct Answer
Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic
Your Answer
Change in physical characteristic , Consumption of physical effort , Movement of material

True/False
Question
An activity can share the same tail event and same head event with any other activity.
Correct Answer
False
Your Answer
True

Select The Blank
Question
The ________ must ensure that the product satisfy the functional requirements of it's usage.
Correct Answer
Quality of design
Your Answer
Quality of design

Multiple Choice Multiple Answer
Question
Which of the following are examples of pure materials?
Correct Answer
Bakeries , Ice factories , Woolen
Your Answer
Bakeries , Ice factories , Woolen

Select The Blank
Question
The ________ are the definitions of the measurable as well as nonmeasurable characteristics of the product.
Correct Answer
Specifications
Your Answer
Specifications

Multiple Choice Single Answer
Question
Site factors for plant location include
Correct Answer
Suitability of land
Your Answer
Suitability of land

Select The Blank
Question
The ________ is the probability that a good lot will be rejected by the sampling plan.
Correct Answer
Producer's risk
Your Answer
Producer's risk

Multiple Choice Multiple Answer
Question
Which of the following defects can be observed during preventive inspection by using human senses?
Correct Answer
Deviation from normal sound , Excessive Vibration , Leakage of a gas
Your Answer
Deviation from normal sound , Excessive Vibration , Leakage of a gas

Select The Blank
Question
The ________ includes preventive maintenance activities whose needs are identified through inspection which requires stoppage of machines.
Correct Answer
Shutdown Maintenance
Your Answer
Working Maintenance

True/False
Question
Independent float either affects the float of preceding activities or that of succeeding activities.
Correct Answer
False
Your Answer
False

Multiple Choice Multiple Answer
Question
Lack of material planning results in the following
Correct Answer
Over ordering , under ordering , stockouts
Your Answer
Over ordering , under ordering , stockouts

True/False
Question
F W Taylor devised a system for classifying motions into basic divisions called Therbligs
Correct Answer
False
Your Answer
False

Select The Blank
Question
Work study is also called ________ study
Correct Answer
Time and Motion
Your Answer
Time and Motion

Match The Following
Question
Correct Answer
Your Answer
Factor Analysis
Method to evaluate layouts
Technique for evolving and analysis of layouts
Minimization of production delays
Objective of good layout
Objective of good layout
Maximum visibility
Principles of good layout
Principles of good layout
Scale model
Layout analysis
Method to evaluate layouts

Multiple Choice Single Answer
Question
Following is one of the techniques used for Material Planning for high value material
Correct Answer
MRP
Your Answer
MRP

Multiple Choice Single Answer
Question
What do you understand by totality of features and characteristics of a product or service that bears on it's ability to satisfy the customer?
Correct Answer
Quality
Your Answer
Quality

Select The Blank
Question
One detachable ticket is prepared for each ________.
Correct Answer
Operation
Your Answer
Worker

0 Comments:

An Appeal to SCDL students

Dear SCDL Student,

We at http://scdlpapers.blogspot.com tries to collect and spread the knowledge in terms of the solved papers and assignments which we are getting through SCDL Alumni.
Now we request you to help other students through mutual sharing. Please send your assignment questions/papers to "mindgrill@gmail.com" . We will publish them on this blog along with your name.
Your help can be boon for many students to clear their exams.

Best of Luck and waiting for your contributions.

Team @ MindGrill
 

Interview Preparation | Placement Papers