Sunday, April 13, 2008

Maintenance Management - 2

LIST OF ATTEMPTED QUESTIONS AND ANSWERS



True/False
Question
Value analysis is one way to attempt for quality simplification.
Correct Answer
True
Your Answer
False

True/False
Question
The lead time to take the decision is same in private sector companies and government controlled organizations.
Correct Answer
False
Your Answer
False

Multiple Choice Single Answer
Question
Installation & commissioning of a new plant is :-
Correct Answer
Single contract tasks
Your Answer
Single contract tasks

Multiple Choice Single Answer
Question
Who has to prepare training manuals?
Correct Answer
Maintenance Manager
Your Answer
Maintenance Manager

Multiple Choice Multiple Answer
Question
The price of the spare part depends on :-
Correct Answer
Demand and supply position , Urgency of buyer , Level of negotiations
Your Answer
Demand and supply position , Urgency of buyer , Level of negotiations

True/False
Question
Any equipment can be dismantled easily without the help of special tools.
Correct Answer
False
Your Answer
False

Match The Following
Question
Correct Answer
Your Answer
Time taken
As low as possible
As low as possible
Automation
Decrease break down time
Decrease break down time
Utilization of machine
As high as possible
As high as possible
Equipment selection
Purchase dept
Purchase dept

True/False
Question
The hazardous chemicals are divided into 90 groups in decreasing order of hazard.
Correct Answer
False
Your Answer
False

Multiple Choice Multiple Answer
Question
The objective inventory control is :-
Correct Answer
To reduce lead time , To reduce finance cost of inventory , To reduce storage cost of material
Your Answer
To reduce lead time , To reduce finance cost of inventory , To reduce storage cost of material

True/False
Question
Proper communication with related departments can result in increased cost of spare.
Correct Answer
False
Your Answer
False

Multiple Choice Single Answer
Question
The leakage should be monitored by device known as :-
Correct Answer
Leakage detector
Your Answer
Leakage detector

Select The Blank
Question
It is right of an inspector to get help of ________ at any time.
Correct Answer
Higher Authorities
Your Answer
Higher Authorities

Multiple Choice Single Answer
Question
What is the lower limit of the ratio of emergency maintenance to total maintenance time?
Correct Answer
Less then 25 %
Your Answer
Less then 10 %

Multiple Choice Multiple Answer
Question
High quality of workmanship helps maintenance people :-
Correct Answer
For boosting Morale of Maintenance People , In Identification of efficient workers , Rewarding Efficient Workers
Your Answer
For boosting Morale of Maintenance People , In Identification of efficient workers , Rewarding Efficient Workers

Multiple Choice Single Answer
Question
Proper spare part will enhance the life of equipment and will save vital :-
Correct Answer
Capital expenditure
Your Answer
Capital expenditure

Multiple Choice Multiple Answer
Question
With "vendor supplies equipments" what Vendor is suppose to supply?
Correct Answer
Drawings of equipments , Drawings of electrical connection , Views of equipment
Your Answer
Micro films , Drawings of equipments , Views of equipment

Select The Blank
Question
Availability of ________ equipment is considered while deciding maintenance system.
Correct Answer
Stand by
Your Answer
Non-Critical

Multiple Choice Multiple Answer
Question
Which of the following are diagnostics instrument which are used in maintenance management?
Correct Answer
Time Tester , Safety checker for portable electrical tools , Temperature Sensitive Crayons
Your Answer
Safety checker for portable electrical tools , Temperature Sensitive Crayons , Heat Flow sensors

True/False
Question
Computers can be used to predict failures and breakdowns by simulation method well in advance.
Correct Answer
True
Your Answer
True

Multiple Choice Multiple Answer
Question
Maintenance Control system is used to check following?
Correct Answer
Correct starting time of Maintenance activities , Maintenance planning , To get correct feedback
Your Answer
Correct starting time of Maintenance activities , Maintenance planning , To get correct feedback

Multiple Choice Multiple Answer
Question
Following equipment must be tested for correct load bearing capacity :-
Correct Answer
Scaffolding , Ladder , Platform
Your Answer
Scaffolding , Ladder , Platform

Multiple Choice Single Answer
Question
The modern management is composed of evaluation, refinement and integration of functional objectives into an :-
Correct Answer
Integrated corporate goal
Your Answer
Integrated corporate goal

Multiple Choice Single Answer
Question
To ensure high efficiency & Productivity in the maintenance work, the most important thing is :-
Correct Answer
Complete Technical Control
Your Answer
Equipment Management

Multiple Choice Multiple Answer
Question
The 5 S' are related to :-
Correct Answer
Orderliness , Tideness , Purity
Your Answer
Orderliness , Tideness , Purity

Multiple Choice Single Answer
Question
If equipment creates noise above permissible level then :-
Correct Answer
It may produce vibration which may affect other equipment.
Your Answer
It is recommended not to purchase such equipment.

Multiple Choice Single Answer
Question
What is a necessary thing, if management expects workers must do maintenance effectively?
Correct Answer
Training
Your Answer
Training

Multiple Choice Multiple Answer
Question
Where CPM can be used?
Correct Answer
In Construction Business , In Research & Development Projects , Launching new products in Marketing
Your Answer
In Construction Business , In Research & Development Projects , Launching new products in Marketing

True/False
Question
The schedule of lubrication of equipment is not a part of maintenance plan.
Correct Answer
False
Your Answer
False

Multiple Choice Single Answer
Question
When the running machine is making sound what is to be done?
Correct Answer
Locate the noise
Your Answer
Stop the machine

True/False
Question
Chart when prepared uses ' half split' method of fault diagnosis.
Correct Answer
True
Your Answer
True

Multiple Choice Multiple Answer
Question
Water as a fire extinguisher can be applied which is in the form of :-
Correct Answer
Solid stream , Fine spray , Foam
Your Answer
Fine spray , Foam

Multiple Choice Single Answer
Question
Automation of machines is mainly done for :-
Correct Answer
Detecting the failures and save time
Your Answer
Detecting the failures and save time

Select The Blank
Question
________ is the period that elapses between the recognition of the need of spare parts and its fulfillment.
Correct Answer
Lead time
Your Answer
Lead time

Select The Blank
Question
________ are used to monitor the conditions of parts subject to strains due to vibrations in operating conditions.
Correct Answer
Strain Gages
Your Answer
Strain Gages

Multiple Choice Multiple Answer
Question
What is VEN in VEIN analysis?
Correct Answer
Time , Technology
Your Answer
Natural , Time , Technology

Select The Blank
Question
One of the main jobs of ________ is to train the subordinates.
Correct Answer
Supervisor
Your Answer
Supervisor

Match The Following
Question
Correct Answer
Your Answer
Factory building
Cross ventilation
Cross ventilation
Foreign origin equipment
Manual translation into English
Manual translation into English
Non standard spare parts
Maximum lead time
Maximum lead time
Steam piping
Proper Insulation
Proper Insulation

Select The Blank
Question
Quality should not be ________ at the cost of lower price.
Correct Answer
Sacrificed
Your Answer
Sacrificed

Multiple Choice Multiple Answer
Question
What may be the result of too many levels of authority?
Correct Answer
Overlapping of duties , Confusion , No work done
Your Answer
Overlapping of duties , Confusion , No work done

True/False
Question
Some equipments are patented so manufacturing of spares is possible.
Correct Answer
False
Your Answer
False

True/False
Question
Oil pump is lubricating equipment.
Correct Answer
True
Your Answer
False

Select The Blank
Question
Adequate ________ should be provided in the design of the equipment to prevent any mishap.
Correct Answer
Interlocks, safety alarms
Your Answer
Interlocks, safety alarms

Select The Blank
Question
To achieve high reliability we should select ________.
Correct Answer
Trouble free operation machine
Your Answer
Trouble free operation machine

Select The Blank
Question
________ is schedule of overhaul & schedule of calibrating the equipment.
Correct Answer
Maintenance schedule
Your Answer
Maintenance schedule

Select The Blank
Question
The wear out portion has ________ failure rates.
Correct Answer
Highest
Your Answer
Highest

Select The Blank
Question
The spark can be generated due to ________ faults.
Correct Answer
Phase to phase
Your Answer
Ignitions

Multiple Choice Single Answer
Question
What is necessary under good house keeping to avoid sparks & ignition?
Correct Answer
Well designed equipments
Your Answer
Well designed equipments

No comments:

Search Assignments and Papers Here...


Custom Search

An Appeal to SCDL students

Dear SCDL Student,

We at http://scdlpapers.blogspot.com tries to collect and spread the knowledge in terms of the solved papers and assignments which we are getting through SCDL Alumni.
Now we request you to help other students through mutual sharing. Please send your assignment questions/papers to "mindgrill@gmail.com" . We will publish them on this blog along with your name.
Your help can be boon for many students to clear their exams.

Best of Luck and waiting for your contributions.

Team @ MindGrill