LIST OF ATTEMPTED QUESTIONS AND ANSWERS
Multiple Choice Single Answer
Question A set of activities ensure that software correctly implements a specific function is called as software:-
Correct Answer Verification
Your Answer Validation
Select The Blank
Question ________ testing confirms that the needs and requirements are fulfilled in the development environment.
Correct Answer Alpha
Your Answer Alpha
Multiple Choice Single Answer
Question An Activity that has a definite Start and a definite end is termed as ?
Correct Answer Project
Your Answer Project
Multiple Choice Multiple Answer
Question Architecture Design Consists of:-
Correct Answer Module Structure , Program Structure , Hierarchy in the Structure
Your Answer Module Structure , Program Structure , Hierarchy in the Structure
Multiple Choice Multiple Answer
Question The Customer Requirements could be analyzed by:-
Correct Answer Interviewing , Questionnaire , Meeting with Key Users
Your Answer Interviewing , Questionnaire , Meeting with Key Users
Select The Blank
Question In the ________ model data elements are organized in tree structure in parent-child format.
Correct Answer Hierarchical
Your Answer Hierarchical
Multiple Choice Multiple Answer
Question System Testing Techniques are :-
Correct Answer Alpha Test , Beta Test
Your Answer Alpha Test , Beta Test
True/False
Question Stress Testing is a part of Integration testing.
Correct Answer False
Your Answer False
Multiple Choice Multiple Answer
Question The Examples of Business Software are
Correct Answer Payroll ,Accounting, , Inventory , customer Relation Management
Your Answer Payroll ,Accounting, , Inventory , customer Relation Management
Multiple Choice Single Answer
Question A system for the support of software development is called
Correct Answer Computer Aided Software Engineering
Your Answer Computer Aided Software Engineering
Multiple Choice Single Answer
Question At the beginning testing focuses on each component individually, ensuring that it function properly as a unit or not this is termed as:-
Correct Answer Unit Testing
Your Answer Unit Testing
True/False
Question Risk which can be known is termed as unpredictable risk.
Correct Answer False
Your Answer False
True/False
Question Recovery testing focuses on the Cost Recovery Plan of the Software Implemented.
Correct Answer False
Your Answer False
Select The Blank
Question A ________ arises due to uncertainties involved in assessing, estimating various inputs to the software process.
Correct Answer Process Risk
Your Answer Process Risk
True/False
Question Black Box testing Finds out Missing Functions & Interface Errors.
Correct Answer True
Your Answer True
True/False
Question SE is applied for software development through Engineering Methods
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer
Question Legacy software -Poor quality has
Correct Answer Inextensible design , Convoluted Code , Poor or nonexistent documentation
Your Answer Inextensible design , Convoluted Code , Poor or nonexistent documentation
Match The Following
Question Correct Answer Your Answer
Performance Management Efficiency & Effectiveness Efficiency & Effectiveness
Relational Model Data Management With Ease Data Management With Ease
E-R Diagrams Strong & Weak Entities Strong & Weak Entities
Normalization Table Design Table Design
Multiple Choice Single Answer
Question A System is one that is self contained and self reliant:-
Correct Answer Closed System
Your Answer Closed System
Select The Blank
Question ________ type of an error is class I error and needs corrective measures to be implemented immediately.
Correct Answer Fatal
Your Answer Fatal
Select The Blank
Question ________ is characterized by longetivity and business criticality
Correct Answer Legacy Software
Your Answer Legacy Software
Select The Blank
Question The objective of a ________ is to test for what we want to achieve and not what is actually achieved.
Correct Answer Test Plan
Your Answer Test Plan
True/False
Question System testing Starts when Software Integration is about to be completed.
Correct Answer False
Your Answer False
Multiple Choice Single Answer
Question A set of activities ensure that the software that has been built is traceable to customer requirements:-
Correct Answer Validation
Your Answer Validation
Multiple Choice Single Answer
Question A Design which reduces system complexity , and offers better understanding of the system and its components Behavior is :-
Correct Answer Effective Modular Design
Your Answer Effective Modular Design
Multiple Choice Single Answer
Question What is the tool which enforces consistency in naming the entities across the system?
Correct Answer Data Dictionary
Your Answer Data Dictionary
Multiple Choice Single Answer
Question A process to commit the organisation to start the project and complete the project document providing a broad spectrum of the project is :-
Correct Answer Project Initiation
Your Answer Project Initiation
Multiple Choice Multiple Answer
Question The next development in software engineering is
Correct Answer The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technology
Your Answer The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technology
Multiple Choice Multiple Answer
Question Testing a Design Includes:-
Correct Answer Test Procedures , Test Plans , Design Renew Plans
Your Answer Test Procedures , Test Plans , Design Renew Plans
Match The Following
Question Correct Answer Your Answer
Development of the Software Software Programs Software Programs
Corrective Maintenance Maintenance
Process, Tools & Methods Software Engineering Layers Software Engineering Layers
Requirement Specifications Definition Phase Definition Phase
Multiple Choice Multiple Answer
Question Project Risk Management Includes:-
Correct Answer Risk Avoidance , Risk Mitigation , Risk Prevention
Your Answer Risk Prevention , Risk Avoidance , Risk Mitigation
True/False
Question SRS is one of the cause of not meeting the SQA.
Correct Answer True
Your Answer True
Select The Blank
Question ________ tests confirms that the needs and requirements are fulfilled on the deployment platform.
Correct Answer Beta
Your Answer Beta
Multiple Choice Multiple Answer
Question Operational Testing is carried out by :-
Correct Answer Recovery Testing , Stress Testing , Performance Testing
Your Answer Recovery Testing , Stress Testing , Performance Testing
True/False
Question The Major risk involved in software project is to identify the programmers required and the pay scales of them.
Correct Answer False
Your Answer False
Multiple Choice Multiple Answer
Question Work Break Down Structure can also be traced back to ?
Correct Answer System Requirements Specifications , Requirement Definition & Description
Your Answer System Requirements Specifications , Requirement Definition & Description
Multiple Choice Single Answer
Question The Behavioral Aspect of the System could be Shown using :-
Correct Answer Data Flow Diagrams
Your Answer Data Flow Diagrams
Multiple Choice Single Answer
Question A degree to which the design aspect of the Quality is met is termed as :-
Correct Answer Quality Conformance
Your Answer Quality Conformance
True/False
Question System testing checks the abnormality in the software system.
Correct Answer False
Your Answer False
Select The Blank
Question ________ is developed or engineered not manufactured
Correct Answer Software
Your Answer Software
Select The Blank
Question Requirements Management Begins with ________.
Correct Answer Identification
Your Answer Identification
Select The Blank
Question Each & every ________ has a Specific format as a record.
Correct Answer Test
Your Answer Test
Multiple Choice Multiple Answer
Question Test Case Design for real time systems strategically should include:-
Correct Answer Task Testing , Behavioral Testing , Intertask Testing
Your Answer Task Testing , Behavioral Testing , Intertask Testing
True/False
Question The Unit of the Software is the smallest entity to be tested.
Correct Answer True
Your Answer True
Select The Blank
Question ________ is achieved by carving out a module that is responsible for any unique function and which does not need to interact with other parts of the system.
Correct Answer Functional Dependency
Your Answer Functional Dependency
Multiple Choice Multiple Answer
Question The most affected elements of the Quality of the software is:-
Correct Answer Customer , Developer , Stake Holders
Your Answer Customer , Developer , Stake Holders
Multiple Choice Single Answer
Question The Paradigm Structured System Analysis and Design was developed by:-
Correct Answer Yourdon & De Macro
Your Answer Yourdon & De Macro
Welcome to the Symbiosis Center for Distance Learning(SCDL) blog. This blog is for the students of SCDL who are doing post graduate diplomas in management from Symbiosis Center for Distance Learning SCDL Pune. Here they can get solved assignments and exam related information. It contains assignments for PGDBA PGDBFS PGDHRM PGDP&HRM PGDIB PGDEXIM, PGDBCL PGDCRMPGDSCM PGDRM, PGDDS PGDIT PGDPM PGDEM PGDTWBM PGDIBM PGDEA PGDID PGDSC PGDPTT PGPAM PGDJMC PGDPC PGCBA PGPF PGCHM PGCDT PGCFMA etc
Subscribe to:
Post Comments (Atom)
Search Assignments and Papers Here...
Custom Search
An Appeal to SCDL students
Dear SCDL Student,
We at http://scdlpapers.blogspot.com tries to collect and spread the knowledge in terms of the solved papers and assignments which we are getting through SCDL Alumni.
Now we request you to help other students through mutual sharing. Please send your assignment questions/papers to "mindgrill@gmail.com" . We will publish them on this blog along with your name.
Your help can be boon for many students to clear their exams.
Best of Luck and waiting for your contributions.
Team @ MindGrill
We at http://scdlpapers.blogspot.com tries to collect and spread the knowledge in terms of the solved papers and assignments which we are getting through SCDL Alumni.
Now we request you to help other students through mutual sharing. Please send your assignment questions/papers to "mindgrill@gmail.com" . We will publish them on this blog along with your name.
Your help can be boon for many students to clear their exams.
Best of Luck and waiting for your contributions.
Team @ MindGrill
No comments: