LIST OF ATTEMPTED QUESTIONS AND ANSWERS

Multiple Choice Multiple Answer
Question
Which of the following concepts must be understood for the achievement of quality?
Correct Answer
Quality of design , Quality of conformance , Purpose of product
Your Answer
Quality of conformance , Quality of design

Multiple Choice Single Answer
Question
What do you mean by the graphical representation of the project which is composed as series of connected arrows and circles to describe the interrelationship of the activities involved?
Correct Answer
Network
Your Answer
Network

Multiple Choice Multiple Answer
Question
Which of the following cases indicates change in physical characteristic?
Correct Answer
Turning , Grinding , Drilling
Your Answer
Turning , Grinding , Drilling

Multiple Choice Single Answer
Question
What do you mean by the verification of object against predetermined standards of quality or quantity or both?
Correct Answer
Inspection
Your Answer
Quality assurance

Multiple Choice Single Answer
Question
Any premise in which persons are employed for purpose of making any product/s is called
Correct Answer
Factory
Your Answer
Factory

Select The Blank
Question
The ________ advocates maintenance procedures whereby the condition of the plant is constantly watched through systematic inspection to unearth unhealthy conditions and preventive
Correct Answer
Preventive Maintenance
Your Answer
Preventive Maintenance

Select The Blank
Question
The ________ is the defect level for which lots are regarded as bad lots.
Correct Answer
Lot Tolerance Percentage Defective
Your Answer
Lot Tolerance Percentage Defective

Multiple Choice Single Answer
Question
How non-critical activities are shown in the time chart during project scheduling?
Correct Answer
Thin lines
Your Answer
Thin lines

Select The Blank
Question
An ________ history card is the record of all repairs, replacements and engineering changes carried out in the equipment during it's period of service.
Correct Answer
Equipment history card
Your Answer
Equipment history card

Multiple Choice Single Answer
Question
Who prepares the daily production report?
Correct Answer
Shop Supervisor
Your Answer
Shop Supervisor

Select The Blank
Question
Work study is also called ________ study
Correct Answer
Time and Motion
Your Answer
Motion

True/False
Question
Every network does not necessarily have a critical path.
Correct Answer
False
Your Answer
False

Select The Blank
Question
Production Planning is a centralised activity which includes functions such as ________
Correct Answer
Scheduling
Your Answer
Scheduling

Multiple Choice Single Answer
Question
Which method of critical path determination begins with the end event and moves backward to the start event of the project network?
Correct Answer
Backward pass computation
Your Answer
Backward pass computation

True/False
Question
Scrap allowance is added to net requirement of material while ordering for material
Correct Answer
True
Your Answer
True

True/False
Question
Dust gets mixed with lubricants, forms an abrasive substance and causes pre-mature failure of machinery.
Correct Answer
True
Your Answer
True

Multiple Choice Single Answer
Question
A good plant layout helps in
Correct Answer
Reducing handling costs
Your Answer
Reducing handling costs

True/False
Question
It would not affect the project completion time if non-critical activities take little loner time than planned.
Correct Answer
True
Your Answer
True

Select The Blank
Question
The ________ is the process of withdrawing the equipment from the production line, dismantling it unitwise, visualising defects, effecting adjustments, replacing worn-out parts and finally building it up to get desired accuracies.
Correct Answer
Reconditioning
Your Answer
Reconditioning

True/False
Question
Flow process charts do record movements as well as visual pictures.
Correct Answer
False
Your Answer
False

True/False
Question
Process Planning is concerned with decisions regarding requirement of machines and manpower for meeting customer demand
Correct Answer
False
Your Answer
False

Multiple Choice Single Answer
Question
What is the meaning of " Product features" according to J.M.Juran?
Correct Answer
Quality of design
Your Answer
Quality of design

Multiple Choice Single Answer
Question
Technique which can help an organization to reduce inventory is called
Correct Answer
MRP
Your Answer
MRP

Multiple Choice Multiple Answer
Question
Which of the following are examples of consumption of physical effort during recording for method study?
Correct Answer
Bending , Positioning , Unloading
Your Answer
Bending , Positioning , Drilling

True/False
Question
Objective of Work Study is to improve Productivity
Correct Answer
True
Your Answer
True

Multiple Choice Multiple Answer
Question
Which three of the following options can be used to reduce the duration of activity during project crashing?
Correct Answer
Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries.
Your Answer
Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries.

Multiple Choice Single Answer
Question
Which is the next stage to the inspection based quality control in the historical development of quality management.
Correct Answer
Quality assurance
Your Answer
Quality assurance

Match The Following
Question
Correct Answer
Your Answer
Bottom compartment of control board
Bunch of work orders arranged in a sequence in which they are to be processed.
Bunch of work orders arranged in a sequence in which they are to be processed.
Control board
Pictorial view of machine loading activity
Pictorial view of machine loading activity
Top compartment of control board
Work order of item currently being worked on the machine
Work order of item currently being worked on the machine
Middle compartment of control board
Work order of item to be processed next on the machine
Work order of item to be processed next on the machine

Select The Blank
Question
The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking.
Correct Answer
Condition monitoring
Your Answer
Condition monitoring

Select The Blank
Question
The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________.
Correct Answer
Overtime working
Your Answer
Overtime working

Multiple Choice Multiple Answer
Question
Following are some of the Principles of Management advocated by F W Taylor
Correct Answer
Selection of best worker for each particular task , Division of work between worker and management , Training and development of the workmen
Your Answer
Selection of best worker for each particular task , Division of work between worker and management , Training and development of the workmen

Multiple Choice Multiple Answer
Question
How the concept of float is helpful to planners?
Correct Answer
To decide priorities in allocation of resources , To minimize the requirement of resources , To prevent peaks and valleys in requirement of resources
Your Answer
To decide priorities in allocation of resources , To minimize the requirement of resources

Multiple Choice Single Answer
Question
The process of changing inputs into outputs thereby adding some value to entity can be defined as
Correct Answer
Operation
Your Answer
Operation

Multiple Choice Single Answer
Question
Which kind of defect can be called as minor defect?
Correct Answer
Which does not reduce the usability of the product for its intended use
Your Answer
Which does not reduce the usability of the product for its intended use

Select The Blank
Question
The ________ is specified to indicate the maximum permissible variability in the dimensions product or parts.
Correct Answer
Tolerance
Your Answer
Tolerance

True/False
Question
Sampling inspection is best suited when cost of inspection is much higher than the loss arising from the acceptance of a defective part.
Correct Answer
True
Your Answer
False

Multiple Choice Single Answer
Question
Which element of a network represents a task which has got a definite beginning and definite end?
Correct Answer
Activity
Your Answer
Activity

Multiple Choice Multiple Answer
Question
Following are the commonly used factors considered for evaluation of layout in factor analysis method
Correct Answer
Flow of material , Equipment utilization , Working condition
Your Answer
Flow of material , Equipment utilization , Working condition

Select The Blank
Question
A good maintenance system is not a luxary but a ________.
Correct Answer
Necessity
Your Answer
Necessity

Select The Blank
Question
The ________ are the definitions of the measurable as well as nonmeasurable characteristics of the product.
Correct Answer
Specifications
Your Answer
Standards

Multiple Choice Multiple Answer
Question
Which features should be covered by the specifications of materials while defining the qualitative requirement?
Correct Answer
Material composition , Dimensions , Any heat treatment if required
Your Answer
Material composition , Dimensions , Any heat treatment if required

Multiple Choice Single Answer
Question
The ratio of output to input of a production system is commonly known as
Correct Answer
Productivity
Your Answer
Productivity

True/False
Question
F W Taylor devised a system for classifying motions into basic divisions called Therbligs
Correct Answer
False
Your Answer
False

Multiple Choice Single Answer
Question
Which portion of the perforated route sheet should be signed by the operator or supervisor?
Correct Answer
Lower portion
Your Answer
Lower portion

True/False
Question
In case of X bar, if the process is not under control indicated by some points falling outside the control limits, such points outside the control limits are eliminated and new trial control limits for the remaining points are computed.
Correct Answer
True
Your Answer
True

Match The Following
Question
Correct Answer
Your Answer
Scale model
Layout analysis
Modelling approach to layouts
Factor Analysis
Method to evaluate layouts
Technique for evolving and analysis of layouts
Minimization of production delays
Objective of good layout
Objective of good layout
Maximum visibility
Principles of good layout
Principles of good layout

True/False
Question
Maintenance function must be decentralised apart from a size of a manufacturing organisation for it's better functioning.
Correct Answer
False
Your Answer
True

0 Comments:

An Appeal to SCDL students

Dear SCDL Student,

We at http://scdlpapers.blogspot.com tries to collect and spread the knowledge in terms of the solved papers and assignments which we are getting through SCDL Alumni.
Now we request you to help other students through mutual sharing. Please send your assignment questions/papers to "mindgrill@gmail.com" . We will publish them on this blog along with your name.
Your help can be boon for many students to clear their exams.

Best of Luck and waiting for your contributions.

Team @ MindGrill
 

Interview Preparation | Placement Papers