Friday, September 12, 2008

Production and Operations Management - 11

POM assgn
Select The Blank
Question
The ________ must ensure that the product satisfy the functional requirements of it's usage.
Correct Answer
Quality of design
Your Answer
Quality of design

Multiple Choice Multiple Answer
Question
Which of the following information is available in summary of part in a chart during methods study?
Correct Answer
Frequency of each symbol , Total time for each symbol , Total distance travelled by the object
Your Answer
Frequency of each symbol , Total time for each symbol

True/False
Question
The event numbers as far as possible reflect the logical relationships of the activities.
Correct Answer
True
Your Answer
False

Multiple Choice Single Answer
Question
Which varaible is taken along the ordinate or Y axis?
Correct Answer
Quality
Your Answer
Quality

Multiple Choice Multiple Answer
Question
Which of the following schedules are recommended to prepare and follow as a part of preventive maintenance system?
Correct Answer
Preventive inspection schedule , Cleaning and upkeep schedule , Lubrication schedule
Your Answer
Preventive inspection schedule , Cleaning and upkeep schedule , Lubrication schedule

Multiple Choice Single Answer
Question
Which kind of preventive inspection detects some maintenance related characteristics by making use of human senses, when equipment is in operation?
Correct Answer
Extrernal inspection
Your Answer
Extrernal inspection

Multiple Choice Multiple Answer
Question
Which are different ways to show critical path in a network?
Correct Answer
Thick Line , Red Line , Double Line
Your Answer
Thick Line , Red Line , Double Line

Multiple Choice Multiple Answer
Question
What are the benefits of overhauling?
Correct Answer
It increases useful life of an equipment and it's parts , Advance planning allows to attend equipment without disturbing the production programme , Advance planning allows to prepare and keep ready the list of replacement spares
Your Answer
It increases useful life of an equipment and it's parts , Advance planning allows to attend equipment without disturbing the production programme , Advance planning allows to prepare and keep ready the list of replacement spares

Match The Following
Question
Correct Answer
Your Answer
Combined Layout
Mixed Layout
Mixed Layout
Fixed Position Layout
Project Layout
Line Layout
Product Layout
Line Layout
Shop layout
Process Layout
Functional Layout
Functional Layout

Multiple Choice Multiple Answer
Question
Which of the following factors play important role while selecting or rejecting a particular site from legislation and taxation point of view?
Correct Answer
Labour laws , Building codes , Policies regarding issue of licences
Your Answer
Labour laws , Building codes , Policies regarding issue of licences

Select The Blank
Question
The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average.
Correct Answer
Acceptable quality level
Your Answer
Acceptable quality level

Multiple Choice Multiple Answer
Question
Major contributors in the development of Control Charts, Sampling plan are
Correct Answer
F H Dodge , H G Roming , Walter Schewhart
Your Answer
F H Dodge , H G Roming , Walter Schewhart

True/False
Question
Skill of labour force in a product type layout is usually higher than in the process type of layout
Correct Answer
False
Your Answer
True

True/False
Question
Repetitive movements between work stations which are difficult to be traced on string diagrams can be conveniently shown on flow diagrams.
Correct Answer
False
Your Answer
True

Select The Blank
Question
The ________ is necessary when the job requires detailed of one or more of the job characteristics with the help of special equipment which is not available at the producing company.
Correct Answer
Inspection order
Your Answer
Job card

Multiple Choice Multiple Answer
Question
Which of the following cases can be referred as operation in method study recording?
Correct Answer
Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic
Your Answer
Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic

Select The Blank
Question
The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking.
Correct Answer
Condition monitoring
Your Answer
Overhauling

True/False
Question
All activities lying on the non-critical paths must have total float and free float.
Correct Answer
False
Your Answer
False

Select The Blank
Question
Work study is also called ________ study
Correct Answer
Time and Motion
Your Answer
Method

Match The Following
Question
Correct Answer
Your Answer
Crash cost of an activity
Cc
Cc
Normal time of an activity
Tn
Tn
Crash time of activity
Tc
Tc
Normal cost of an activity
Cn
Cn

Multiple Choice Multiple Answer
Question
Which are the advantages of suburban location?
Correct Answer
Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction
Your Answer
Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction

True/False
Question
In case of X bar-R charts,it is ensured that the assignable causes are detected before the tolerances are violated, upper and lower statistical limits are worked out and inserted into a chart.
Correct Answer
True
Your Answer
False

Multiple Choice Single Answer
Question
Which of the following is the criteria for the percentage defectives in the zone of the indecision?
Correct Answer
Lots having the percentage defective more than AQL but less than LPTD
Your Answer
Lots having the percentage defective less than AQL but more than LPTD

Select The Blank
Question
The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________.
Correct Answer
Overtime working
Your Answer
Overtime working

Multiple Choice Single Answer
Question
What do you mean by lowest possible direct cost required to complete an activity within it's crashed time?
Correct Answer
Crash cost
Your Answer
Crash cost

Multiple Choice Single Answer
Question
In case of Batch Production which kind of labour is expected?
Correct Answer
Skilled in one specific Manufacturing Process
Your Answer
Semiskilled

Multiple Choice Multiple Answer
Question
Which three of the following are causes of continuous upward pattern of Xbar-R control chart?
Correct Answer
Wear of tool , Abnormal rise in temperature , Accumulation of dirt
Your Answer
Wear of tool , Abnormal rise in temperature , Accumulation of dirt

True/False
Question
Root cause of most of the breakdowns is failure of the lubrication system.
Correct Answer
True
Your Answer
True

True/False
Question
It is not necessary to know spare time available on the non-critical path to allow a little delay for noncritical activity.
Correct Answer
False
Your Answer
False

True/False
Question
MRP software generates time periodwise requiremetn of subassemblies
Correct Answer
True
Your Answer
True

True/False
Question
In case of two handed process chart, the simultaneous activities of both hands are recorded opposite to each other on the chart.
Correct Answer
True
Your Answer
True

Multiple Choice Single Answer
Question
What do you mean by CPM?
Correct Answer
Critical Path Method
Your Answer
Critical Path Method

Multiple Choice Multiple Answer
Question
Which of the following are major inputs to scheduling?
Correct Answer
Overlapping of operations , Effective Capacity per work centre , Performance standards
Your Answer
Overlapping of operations , Effective Capacity per work centre , Performance standards

Multiple Choice Multiple Answer
Question
Lack of material planning results in the following
Correct Answer
Over ordering , under ordering , stockouts
Your Answer
Over ordering , under ordering , stockouts

Multiple Choice Single Answer
Question
What do you mean by the verification of object against predetermined standards of quality or quantity or both?
Correct Answer
Inspection
Your Answer
Inspection

Multiple Choice Multiple Answer
Question
What are the advantages of templates over diagrams?
Correct Answer
Can be conveniently moved on the graph paper , Less laborious , Saves time
Your Answer
Can be conveniently moved on the graph paper , Less laborious , Unskilled person can do and analyze it

True/False
Question
It would not affect the project completion time if non-critical activities take little loner time than planned.
Correct Answer
True
Your Answer
True

Select The Blank
Question
The ________ is the probability that a good lot will be rejected by the sampling plan.
Correct Answer
Producer's risk
Your Answer
Producer's risk

Multiple Choice Single Answer
Question
Any premise in which persons are employed for purpose of making any product/s is called
Correct Answer
Factory
Your Answer
Factory

Select The Blank
Question
An Ideal OC curve is ________ shaped curve that accpets all the lots with quality equal to or better than AQL .
Correct Answer
Rectangular
Your Answer
Bell

Multiple Choice Single Answer
Question
Which is the right time to prepare stores issue order?
Correct Answer
When route sheet is ready
Your Answer
When route sheet is ready

Multiple Choice Single Answer
Question
Which element of a network represents a task which has got a definite beginning and definite end?
Correct Answer
Activity
Your Answer
Activity

Multiple Choice Single Answer
Question
Which kind of preventive inspection detects some defects in moving parts, internal cracks, and others , when machine is under preplanned shutdown?
Correct Answer
Internal inspection
Your Answer
Internal inspection

Select The Blank
Question
Production Planning is a centralised activity which includes functions such as ________
Correct Answer
Scheduling
Your Answer
Dispatching

Select The Blank
Question
The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable.
Correct Answer
Quality control
Your Answer
Quality control

Select The Blank
Question
Goods after final inspection should accompany ________to enable dispatch department to identify and draw correct reference.
Correct Answer
Forwarding note
Your Answer
Forwarding note

Multiple Choice Single Answer
Question
Who has introduced the useful concept of control chart in 1931?
Correct Answer
Walter Shewhart
Your Answer
Walter Shewhart

No comments:

Search Assignments and Papers Here...


Custom Search

An Appeal to SCDL students

Dear SCDL Student,

We at http://scdlpapers.blogspot.com tries to collect and spread the knowledge in terms of the solved papers and assignments which we are getting through SCDL Alumni.
Now we request you to help other students through mutual sharing. Please send your assignment questions/papers to "mindgrill@gmail.com" . We will publish them on this blog along with your name.
Your help can be boon for many students to clear their exams.

Best of Luck and waiting for your contributions.

Team @ MindGrill