Search Assignments and Papers Here...


Custom Search

Saturday, December 6, 2008

Production Planning and Control - 1

LIST OF ATTEMPTED QUESTIONS AND ANSWERS



Multiple Choice Single Answer
Question
The sourcing of vendors in case of 'B' type of items is :-
Correct Answer
Medium
Your Answer
Minimum

Select The Blank
Question
In the assignment model, the________ is formed between jobs and machines.
Correct Answer
Matrix
Your Answer
Matrix

Select The Blank
Question
Production Planning and Control department acts as a link between company's sales and ________ department.
Correct Answer
Manufacturing
Your Answer
Manufacturing

Select The Blank
Question
________ is used for planning capacity.
Correct Answer
Standard Time
Your Answer
Standard Time

Select The Blank
Question
Being capable to adjust their production facilities shortly just after change in demand for products and without incurring heavy expenses, greater flexibility in production is provided by ________.
Correct Answer
Job & batch production
Your Answer
Continuous production

True/False
Question
PERT uses linear programming and probability concepts for planning and controlling activities.
Correct Answer
True
Your Answer
True

Multiple Choice Single Answer
Question
Proper Production Planning and Control can reduce cost in :-
Correct Answer
Overtime cost
Your Answer
Overtime cost

Multiple Choice Single Answer
Question
Detachable ticket, after filling in required information is :-
Correct Answer
Placed in a tray/box
Your Answer
Placed in a tray/box

Select The Blank
Question
The effectiveness of sequencing model technique ________ if the company has backlog of orders.
Correct Answer
Increases
Your Answer
Decreases

Multiple Choice Multiple Answer
Question
Computerisation of line balancing involve following requirements :-
Correct Answer
System software , Application software , User friendly interface
Your Answer
System software , Application software , User friendly interface

True/False
Question
Curve fitting method of statistical forecasting uses curve line approach.
Correct Answer
False
Your Answer
False

True/False
Question
If set up time for four operations involved is 2 ,1.5, 2 , 2.5 hours respectively, total set up time would be 10 hours.
Correct Answer
False
Your Answer
False

Match The Following
Question
Correct Answer
Your Answer
Bought out materials required for production process but do not become part of finished product.
Maintenance, repair, operating [MRO] inventories
Maintenance, repair, operating [MRO] inventories
Finished goods, ready for sale to customer
Finished goods inventory
Finished goods inventory
Idle resource of any kind having economic value
Inventory
Inventory
Raw materials, parts, components required to produced finished product
Production inventory
Production inventory

Select The Blank
Question
Rational figure on utilization index can be obtained by carrying out ________ study.
Correct Answer
Work- sampling
Your Answer
Work- sampling

Multiple Choice Single Answer
Question
The assignment algorithm was developed by a Hungarian mathematician named :-
Correct Answer
D. Konig
Your Answer
D. Konig

Multiple Choice Multiple Answer
Question
The minimum requirements for application software for line balancing are as follows :-
Correct Answer
1 Ghz processor , 1 Gb hard Disk free memory , Windows or equivalent operating system.
Your Answer
1 Ghz processor , 1 Gb hard Disk free memory , Windows or equivalent operating system.

Multiple Choice Multiple Answer
Question
A firm has 6 jobs to be processed on three machines A,B and C in the order ABC. The processing time of each job is given in the table below:- Find the idle time on different machines . Job Processing time [ hours ] Machine A Machine B Machine C J1 25 16 20 J2 26 20 19 J3 24 17 18 J4 22 20 21 J5 24 21 17 J6 28 18 13
Correct Answer
74 , 31 , 58
Your Answer
31 , 58 , 60

Multiple Choice Multiple Answer
Question
PERT terminology uses words like :-
Correct Answer
Network diagram , Events , Slack
Your Answer
Network diagram , Events , Slack

Multiple Choice Single Answer
Question
The most common assembly line is a moving conveyor that passes a series of workstations in a uniform time interval called :-
Correct Answer
Cycle time
Your Answer
Cycle time

True/False
Question
The make-or-buy decision is not related with profit of the factory.
Correct Answer
False
Your Answer
True

Select The Blank
Question
Generally for ________ flow system, Heuristic method is preferred.
Correct Answer
Intermittent
Your Answer
Intermittent

Multiple Choice Single Answer
Question
Document raised by sales department to authorise activities of PPC department for items manufactured to customers order is called :-
Correct Answer
Order Acceptance
Your Answer
Order Acceptance

Multiple Choice Multiple Answer
Question
What factors affect the status of PPC department in the company for achieving informal status?
Correct Answer
Manufacturing Process , Work is highly repetitive , Number of workmen is not very large
Your Answer
Manufacturing Process , Work is highly repetitive , Number of workmen is not very large

True/False
Question
Increase in inventory carrying cost increases EOQ.
Correct Answer
False
Your Answer
False

True/False
Question
Progressing is only a substitute for poor planning.
Correct Answer
False
Your Answer
True

Multiple Choice Multiple Answer
Question
Detachable Card contain following information :-
Correct Answer
Quantity produced , Operation , Date of completion
Your Answer
Quantity produced , Operation , Date of completion

Multiple Choice Multiple Answer
Question
Weaknesses of PPC department can be studied on following grounds :-
Correct Answer
Failures in delivery commitment , Cancellation of orders , Complaints from customers
Your Answer
Failures in delivery commitment , Cancellation of orders , Complaints from customers

Multiple Choice Single Answer
Question
Activity R can not start unless activities P & Q are completed . And activity S can not start unless activity Q is over [ I.e. activity P may not be even over ]. Activity R is therefore succedding to activity P & Q while activity S is succeeding to activity :-
Correct Answer
Q
Your Answer
Q

Multiple Choice Single Answer
Question
If the annual usage of a material is 1200 units and the reorder point is at 120 Units, find the lead time.
Correct Answer
4 months
Your Answer
4 months

Multiple Choice Multiple Answer
Question
Due to the following emergent events, the queue time has to compensate for the time for which the job has to undergo an extra time :-
Correct Answer
Tool breakage , Job split up , Change in priorities
Your Answer
Tool breakage , Job split up , Change in priorities

True/False
Question
Stores issue order for an item is prepared as soon as the route sheet is ready.
Correct Answer
True
Your Answer
True

Multiple Choice Single Answer
Question
Time study is useful method of measurement for :-
Correct Answer
Short cycle time operations
Your Answer
Long cycle time operations

Match The Following
Question
Correct Answer
Your Answer
Index method
Loading and allocation of different jobs on different machines
Loading and allocation of different jobs on different machines
Critical Path Analysis
Schedule of activities of project
Schedule of activities of project
Jonsons method
Optimal job sequence for 2 machines n jobs
Schedule using priority numbers
Critical Ratio Scheduling
Establishing priorities among jobs
Establishing priorities among jobs

Select The Blank
Question
In check list approach, ________ rating indicates that existing PPC system requires some major improvements in indicated areas.
Correct Answer
Fair
Your Answer
Fair

Multiple Choice Multiple Answer
Question
Because of following reasons there are limitations in forwarding quotation against sales enquiry :-
Correct Answer
The lot is not as per EOQ , Tools / plants required to execute order are not available. , The item is not within the manufacturing range of a company
Your Answer
The lot is not as per EOQ , Tools / plants required to execute order are not available. , The item is not within the manufacturing range of a company

Multiple Choice Multiple Answer
Question
Following are the factors which influence tool life :-
Correct Answer
Type of tool , Material it is required to operate upon , Operators efficiency
Your Answer
Type of tool , Material it is required to operate upon , Operators efficiency

True/False
Question
C type items would never be vital under VED analysis.
Correct Answer
False
Your Answer
False

Multiple Choice Multiple Answer
Question
The Hungarian method is based on following assumptions :-
Correct Answer
Tasks differ in their work contents and facility differ in their capabilities. , Only one task can be assigned to each facility. , As only one task can be assigned to each facility, the matrix must be of nXn order.
Your Answer
Tasks differ in their work contents and facility differ in their capabilities. , Only one task can be assigned to each facility. , As only one task can be assigned to each facility, the matrix must be of nXn order.

Multiple Choice Single Answer
Question
The ratio between "time when a product is required" and " time when the product is supplied " is known as :-
Correct Answer
Critical ratio
Your Answer
Critical ratio

Select The Blank
Question
________ inventories help to balance company's supply with market demand.
Correct Answer
Finished goods
Your Answer
Finished goods

True/False
Question
In order to complete a project on time, each critical activity need not be completed in time.
Correct Answer
False
Your Answer
False

Multiple Choice Single Answer
Question
Production output in night shift is :-
Correct Answer
Less than I shift production
Your Answer
Less than I shift production

Select The Blank
Question
________reflects impact of money tied up in inventory.
Correct Answer
Inventory turnover
Your Answer
Inventory turnover

Multiple Choice Multiple Answer
Question
The line of balance is a device for planning and monitoring progress of :-
Correct Answer
Purchase order execution , Project execution , Targeted programs
Your Answer
Purchase order execution , Project execution , Targeted programs

Select The Blank
Question
Forecasting is function of ________.
Correct Answer
Marketing department
Your Answer
Chief Executive officer

True/False
Question
The Heuristics approach has a base of binary number theory.
Correct Answer
False
Your Answer
True

Multiple Choice Single Answer
Question
What shall be the consequence of acceptance of frequent rush orders by sales department?
Correct Answer
Delivery failure
Your Answer
Disturbed scheduling

0 Comments:

An Appeal to SCDL students

Dear SCDL Student,

We at http://scdlpapers.blogspot.com tries to collect and spread the knowledge in terms of the solved papers and assignments which we are getting through SCDL Alumni.
Now we request you to help other students through mutual sharing. Please send your assignment questions/papers to "mindgrill@gmail.com" . We will publish them on this blog along with your name.
Your help can be boon for many students to clear their exams.

Best of Luck and waiting for your contributions.

Team @ MindGrill
 

Interview Preparation | Placement Papers