Multiple Choice Single Answer
|
|
Question
|
Which of the following technique
is event oriented ?
|
Answer
|
Project Evaluation & Review
Technique
|
Multiple Choice Single Answer
|
|
Question
|
What is the meaning of "
Product features" according to J.M.Juran?
|
Answer
|
Quality of design
|
Match The Following
|
|
Question
|
Answer
|
Crash
cost of an activity
|
Cc
|
Normal
time of an activity
|
Tn
|
Crash
time of activity
|
Tc
|
Normal
cost of an activity
|
Cn
|
Multiple Choice Multiple Answer
|
|
Question
|
What are uses of diagrams in
method study?
|
Answer
|
Study different plant layouts and
select the most optimum one , Study the extent of traffic over the different
routes of the plant , Identify the extent of backtracking, cross traffic and
obstacles encountered during the movement of material.
|
True/False
|
|
Question
|
A load chart specifies the work
to be carried out by each person of company during shift hours.
|
Answer
|
FALSE
|
Multiple Choice Multiple Answer
|
|
Question
|
Route Sheet generally contains
following information
|
Answer
|
Material Specification , Sequence
of operation , Skill of Labour
|
True/False
|
|
Question
|
Cellular layout is based on the
concept of Group Technology
|
Answer
|
TRUE
|
Multiple Choice Single Answer
|
|
Question
|
Which varaible is taken along the
abscissa or X axis?
|
Answer
|
Time
|
Multiple Choice Multiple Answer
|
|
Question
|
Which are the advantages of
suburban location?
|
Answer
|
Avaialability of adequate land at
lower cost , Both skilled and unskilled labour can be available , Plant
expansion is easier due to less or no restriction for building and
construction
|
Select The Blank
|
|
Question
|
The ________ is the maintenance
work initiated on a result of knowledge of the condition of an item from
routine or continuous checking.
|
Answer
|
Condition monitoring
|
Multiple Choice Multiple Answer
|
|
Question
|
Expediting function is concerned
with following activities
|
Answer
|
Progress chasing to identify
delays which may hold up production , Communicating possible delays in
delivery date commitment to sales department , Devising cures to keep rate of
production in line with schedule
|
Select The Blank
|
|
Question
|
Production control work is
________ in case of floor inspection as compared with the centralised
inspection.
|
Answer
|
easier
|
Select The Blank
|
|
Question
|
The easiest way to bring the
delayed job within the promised delivery time by using extra shift or weekly
holiday is ________.
|
Answer
|
Overtime working
|
True/False
|
|
Question
|
In case of forward pass
computation, the earliest event time of the first event is zero.
|
Answer
|
TRUE
|
Multiple Choice Single Answer
|
|
Question
|
What is represented by an arrow
in a network?
|
Answer
|
Activity
|
True/False
|
|
Question
|
As a general rule, a site five
times the actual plant size is considered minimum for parking, access
facilities and future expansion.
|
Answer
|
TRUE
|
True/False
|
|
Question
|
Independent float either affects
the float of preceding activities or that of succeeding activities.
|
Answer
|
FALSE
|
Multiple Choice Single Answer
|
|
Question
|
The document raised by PPC which
authorises different functions to take action as per instruction is called
|
Answer
|
Work Order
|
Multiple Choice Single Answer
|
|
Question
|
A good layout makes effective use
of space. Utilization of space for a department like Stores can be measured
by
|
Answer
|
Proportion of Cubic volume space
utilized
|
Multiple Choice Single Answer
|
|
Question
|
The process of changing inputs
into outputs thereby adding some value to entity can be defined as
|
Answer
|
Operation
|